Requirement
Define the final component face, axis and position at the receiving tool, permitted contact or support surfaces and acceptable component condition. State the usable delivery and demand pattern required by that process.

Prepare feeder-track specifications with component tolerances, contact limits, final datum, track transitions, buffer, escapement, downstream demand and recovery records.
Define the component range and the final face, axis and position required by the receiving tool. Supply current drawings and production-condition samples, permitted support features and marking limits. Describe transitions, buffer needs, part-present sensing and single-part release, including what happens at no demand, a blocked destination and interrupted transfer.
Use the geometry and variation brief and accepted-delivery evidence plan. Separate confirmed requirements, assumptions, variant settings and issues still needing representative trials.
Plan feeder tracks and presentation tooling around real component variation, bulk condition, orientation, usable delivery rate and the downstream interface. Discuss representative part trials with Sorting Solutions. A clear brief should state the operating range for component geometry and variation for feeder tracks & presentation tooling and your requirements for jam, damage and recovery acceptance checks.
Discuss your application

Define the final component face, axis and position at the receiving tool, permitted contact or support surfaces and acceptable component condition. State the usable delivery and demand pattern required by that process.
Include normal component tolerances, finish, lubrication and supplier variations. Describe track transitions, accumulation and the full, draining and nearly empty conditions, with variant settings and interchangeable tooling identified.
Trial the complete track and release sequence against agreed final-position and condition checks. Include no demand, a blocked destination, restart and interrupted transfer, retaining accepted delivery, jams, marking and controlled-recovery results.
For feeder tracks and presentation tooling, use “shall” only for a requirement that can be demonstrated. Keep preferences, assumptions, provisional line connections and future options clearly separate.
Your final feeder tracks and presentation tooling scope must also account for escapement and downstream pick interface, jam, damage and recovery acceptance checks, current regulations and the conditions at your site.